Cement PreHeater t ower
Reduction of material build up: Prior to the plant stop, as much build up should be removed as practical, by manipulating process conditions. safety standards should be maintained whether the work is planned or unplanned and as a general principle the order of work should be as follows: Work from top Down, Initial external Clean